Acceptance criteria, delivered configuration, test evidence, punch-list closure and shipment release

Bottom line: A leveling machine factory acceptance test is a documented comparison between the machine offered for shipment and the approved project requirements. It should identify the exact machine and configuration, demonstrate agreed functions, record any representative-material test and measurement method, close deviations, and confirm the document and packing package. A generic list of fixed tolerances cannot replace the signed FAT protocol.

Agree the criteria firstFreeze the purchase specification, approved drawings, FAT protocol, test material and release authority before the witness date.
Test the delivered scopeMatch the model, identification, options, controls and interfaces to the order instead of testing an assumed standard machine.
Close the evidenceRecord results, instrument identity, deviations, retests, documents and packing status before shipment is released.

FAT sequence: Freeze the criteria → verify machine identity and configuration → inspect mechanical and roller systems → complete the agreed pre-start and no-load tests → run the representative-material test when required → record measurements → close the punch list → verify documents and packing → obtain written shipment release.
compact leveling machine with roller entry and electrical control box
Representative compact leveling machine with a visible roller entry and control box. The photo supports machine and component identification only; it does not show a completed test or an accepted result.

Which documents define the FAT pass/fail criteria?

Start the FAT by listing the controlled documents and their current revisions. The buyer and supplier should know which document controls if a brochure, quotation, drawing and test sheet describe a requirement differently. Put the agreed acceptance value, measurement method and responsible witness in the protocol before testing begins.

Controlled input What it should define What to record at FAT
Purchase order and technical specification Contract scope, material range, required functions, documentation, witness and release conditions Document number, revision and any approved clarification
Approved machine drawing or data sheet Model, arrangement, working direction, interfaces, dimensions and supplied options Drawing revision and configuration comparison
Signed FAT protocol Test sequence, acceptance criteria, material, sample method, instruments, witnesses and evidence format Actual result, status, comments and signatures for each line item
Electrical, pneumatic or hydraulic documents Delivered circuits, component identification, supply data and interface responsibilities where applicable Revision, point checks, alarms and controlled exceptions
Software and parameter record, when applicable Approved program/version, access responsibility, backups and recoverable parameter set for the delivered controls Version or backup identity and handover owner
Packing and document requirements Manuals, drawings, loose parts, tools, preservation, marks and shipping-release evidence Completed checklist and open-item disposition
There is no responsible universal FAT number. Flatness, gap, parallelism, run duration, temperature, noise, cycle count and other acceptance values must come from the approved project specification, drawing, signed protocol or another contractually identified source—including the applicable edition of any cited standard.

How should machine identity and ordered scope be verified?

The witness should be able to connect every result to one physical machine. Record the machine identification and compare the visible and documented configuration with the order. A correct test on the wrong model, option set or control revision is not useful acceptance evidence.

Machine model, serial or other unique identification, and nameplate data
Working direction, material path, nominal scope and approved layout
Leveling head, roller arrangement and adjustment mechanism for the ordered configuration
Drive, control cabinet, operator interface and supplied operating modes
Guides, supports, guards, sensors and optional devices included in the order
Electrical, pneumatic and hydraulic components where those systems are supplied
Buyer-supplied or third-party interfaces and the boundary of the factory test
Loose parts, tools, spares, manuals and certificates included in the supply scope

Photograph the identification plate and the machine from consistent viewpoints. If an ordered interface cannot be tested because mating equipment is unavailable, mark that limitation in the protocol and define the later site-verification responsibility.

What belongs in the visual, mechanical and roller-system inspection?

Inspect the machine before powered testing so damage, contamination, missing parts or assembly problems are not hidden by later operation. Use the approved drawing, parts list and inspection method for the actual machine.

Inspection area Check Evidence
Frame and assembly Visible condition, fasteners, covers, guards, access panels, labels and agreed finish Checklist status, photographs and deviation reference
Working and support rolls Correct arrangement, clean contact surfaces, visible damage, rotation condition and approved adjustment range Roll identification, observation and specified measurement record
Guides and material path Entry/exit guides, supports and clearances match the approved configuration and intended material path Configuration photograph and drawing comparison
Adjustment mechanism Handles, indicators, actuators or stored settings move and report position as designed Functional observation and reference-position record
Drive and transmission Installed components, guards, lubrication state and visible connection condition Component check and no-load observation
Utilities and controls Nameplate/circuit match, wiring identification, bonding and service connections within the FAT scope Qualified inspection record and controlled document revision
compact leveler showing adjustment handles roller windows and control cabinet
Representative compact leveler showing adjustment handles, roller windows and a control cabinet. These visible features can guide identification; the image does not prove roll geometry, calibration or FAT acceptance.

What should be completed before and during no-load operation?

Before energizing, close the approved pre-start inspection: remove transport restraints as instructed, confirm the required lubrication and utility state, clear tools and people from hazard zones, restore required guards, and place connected equipment in the controlled test condition. Qualified personnel should verify the supply and protective measures against the delivered documentation.

Build the no-load test around observable functions

Start, stop and mode controlDemonstrate the ordered manual, setup and automatic functions that can be safely tested at the factory.
Direction and motionConfirm commanded direction, adjustment movement and indicator response without assuming that motion alone proves accuracy.
Alarms and statusTrigger agreed test conditions, record the expected and observed message/state, and restore the machine through the approved reset path.
Abnormal observationsRecord leakage, overheating, vibration, noise or irregular movement against the protocol’s defined method and limits.

The protocol should state the required operating sequence and duration for the actual machine. Do not convert an old article’s run time, temperature or noise figure into a universal FAT rule.

When is a representative-material leveling test necessary?

Use a material test when the purchase specification or signed FAT plan requires proof with strip or sheet. Agree the material source and condition before the FAT: grade or strength information when known, thickness, width, initial shape, surface condition, sample length and feeding direction. A result is difficult to interpret if the incoming material is not identified.

Record group Minimum traceable information Acceptance source
Input material Material identification, thickness, width, incoming condition, sample orientation and photographs Purchase specification or signed test plan
Machine setup Machine identification, roll/adjustment references, speed or mode, passes if applicable and operator Approved FAT method and machine instructions
Output sample Sample identity, measurement locations, surface observation and retained-sample responsibility Approved drawing/specification and agreed sample plan
Result Actual measured values, method, instrument identity, status and comments—not only “pass” Acceptance criteria listed in the controlled protocol
Representative does not mean convenient. If substitute material is used, record why it is representative, which requirements it can demonstrate, which it cannot, and whether a later test with production material remains open.

How should flatness, surface and measurement evidence be recorded?

Write the measurement method before looking at the result. Define the datum or support condition, sample location and orientation, reference length or area, instrument type, instrument identification and calibration status, repeat method, units and acceptance rule. The record should distinguish the incoming material condition from the leveled output.

Acceptance criterion and its exact document/revision source
Sample identity linked to the material and machine setup record
Measurement diagram or coordinates for each reported location
Instrument identification and calibration/verification status
Actual readings, units and calculation method where applicable
Surface observations under the agreed inspection condition
Witness, date and unedited photographs or video where required
Retest result linked to the original nonconformance

A photograph of a sample on a table is useful context but is not a flatness measurement by itself. Likewise, a machine photo cannot prove roller parallelism or output quality. Keep the visual evidence connected to the measurement record it actually supports.

Which controls, alarms and protective functions should be demonstrated?

Test the functions listed in the approved control and safety documentation for the delivered configuration. Record the test condition, commanded action, expected state, observed state and reset method. Factory simulation may be necessary for interfaces that require other line equipment, but the simulation method and remaining site test must be explicit.

Operating controlsStart/stop, mode selection, direction, adjustment, speed or recipe functions included in the order.
Status and alarmsMachine-ready state, fault indication, sensor states, diagnostic messages and agreed recovery path.
Protective functionsEmergency stop, guards/interlocks and other supplied protective devices tested under the approved safety procedure.
External interfacesDefined I/O, communication and line-permission points, including what remains for integrated site verification.

A FAT is not permission to bypass a protective device for convenience. Safety-related testing and energized inspection belong to qualified personnel working from the approved procedure and local factory controls.

Can a buyer witness the FAT remotely?

Remote witnessing can work when it is agreed in the contract or FAT plan and the evidence package is designed in advance. Send the controlled protocol and machine identity before the session, then use a live agenda that lets the witness connect each demonstration to a line item.

Machine/nameplate view and wide views of the delivered configuration
Live view of operator commands, machine response and relevant indicators
Close views of identified components, samples and instrument displays
Files or recordings named by protocol item, machine identity and date
Actual readings and instrument details entered in the controlled record
Open questions, deviations and retest items assigned before the call closes

Remote video should supplement, not replace, the agreed measurement records and signatures. If the witness cannot see or verify a required condition remotely, keep it open or use the contract’s approved alternative rather than marking it passed by assumption.

How should punch-list items, retests and concessions be closed?

Every failed, incomplete or unverified line item needs a traceable disposition. Record the requirement, actual condition, effect, responsible party, target date and required evidence. After correction, repeat the affected test and any agreed dependent checks.

Status Required control Shipment implication
Corrected and retested Link corrective action and dated retest evidence to the original item Release only after the authorized reviewer accepts the closure
Open before shipment Assign owner, deadline and objective closure evidence Do not treat a verbal promise as a pass
Accepted concession Document the deviation, effect, limits and authorized written acceptance Release only within the signed concession conditions
Deferred site test State why the factory could not test it, the site method, prerequisites and responsibility Keep it distinct from factory-passed items

The final protocol should make the release decision unambiguous: accepted, accepted with listed written conditions, or not released. Preserve the signed record and attachments with the machine document package.

What documents and packing evidence belong before shipment release?

FAT closure and shipping preparation should meet at one release gate. Confirm that the tested machine identity matches the packing list and that corrections completed after the witness test are included in the final record.

Signed FAT protocol, measurement sheets and linked photo/video index
Closed punch list, concessions and deferred-site-test register
Current manuals, approved drawings, parts list and circuit documents
Software/parameter backup identity and access/handover responsibility when applicable to the delivered controls
Loose parts, supplied tools, spares and certificates matched to the order
Cleaning, preservation and transport restraints applied by the approved packing plan
Protected roller and functional surfaces plus capped/identified connections
Package marks, contents list, condition photographs and written release authority

A supplier-capability review before ordering is a different decision. Use the separate factory-audit checklist to examine legal identity, engineering responsibility, workshop capability and document control; use this FAT checklist for the completed machine offered for shipment.

What should a buyer send when requesting a FAT plan?

Send the project data early enough to build the protocol before manufacture is complete. At minimum, provide the material and output requirements, machine configuration, controlled drawings/specification, required functions and interfaces, representative test material plan, measurement method, witness format, documentation list and shipment-release authority.

Product and materialMaterial family, strength/grade when known, thickness/width range, incoming shape and sensitive-surface requirements.
Acceptance methodRequired output, sample plan, measurement definition, instruments/evidence and applicable controlled standard or drawing.
Machine and interfacesOrdered configuration, options, operating modes, upstream/downstream boundaries and site tests that cannot be completed at the factory.
Witness and releaseOnsite or remote witness, attendees, hold points, signatures, punch-list authority, document language and packing-release conditions.

These inputs let the supplier return a project-specific protocol instead of copying generic limits that may not match the machine, material or contract.

Frequently asked questions about leveling machine FAT

What is the difference between a factory audit and a machine FAT?

A factory audit evaluates the supplier’s identity, engineering, workshop and quality-system capability, usually before ordering. A FAT evaluates the completed machine and its evidence against the approved project requirements before shipment. See the separate factory-audit checklist.

Is there one universal flatness tolerance for every leveling machine FAT?

No. The acceptance value and measurement method must come from the purchase specification, approved drawing, signed FAT protocol or another contractually identified source for the project.

Must the FAT use the buyer’s production material?

Use the material agreed in the purchase specification or FAT plan. If substitute material is accepted, record what it represents, its limitations and whether a later test with production material remains open.

Can the FAT be witnessed by video?

Yes, when remote witnessing is agreed and the protocol defines machine identification, live views, readings, files, signatures and unresolved items. Video does not replace required measurement records.

What happens when a FAT item does not pass?

Record the requirement and actual condition, assign corrective action, repeat the affected test, and link the closure evidence. Any concession or deferred site test needs written authorization and defined limits.

What proves that the leveling machine is ready for shipment?

The agreed release authority should sign the completed FAT status after required safety and release-blocking items are closed, any remaining non-safety items are formally controlled, and the document, loose-part, preservation and packing checks are complete.

Define the FAT requirements during machine quotation

Share the machine configuration, material data, output requirement, measurement method, witness plan and release conditions during quotation so the project-specific FAT scope and required evidence can be reviewed.